August 21, 2021 – Infrastructure for Lakeland Central Park’s first phase is underway!
Phase 1 infrastructure includes pre-graded, pad-ready sites for Lots 1-3 to accommodate up to 2 million square feet of industrial space. Lot 2 is projected to be pad-ready in January 2022 followed by the construction of Lakeland Central Park’s first building, a speculative 705,420 sf cross-dock facility to be completed in Q4 2022.
Check out the latest construction progress photos below.