PHASE I INFRASTRUCTURE
- 3 pad-ready sites to accommodate 2.9M SF of industrial space
- Utilities & sidewalk curb & gutter will be substantially complete this month
- Paving & landscaping start in January
- Power & streetlights scheduled for February
- Final completion & turnover to the City targeted for March
BUILDING 2
- Building 2 – 705K SF spec cross-dock facility
- Underground utilities substantially complete
- Final grading & paving begin this month
- Roll-up doors & glass framework are being installed
- Landscaping starts in January
- Delivery scheduled on track for March 2023