Lakeland Central Park Construction Update – December 2022

PHASE I INFRASTRUCTURE

  • 3 pad-ready sites to accommodate 2.9M SF of industrial space
  • Utilities & sidewalk curb & gutter will be substantially complete this month
  • Paving & landscaping start in January
  • Power & streetlights scheduled for February
  • Final completion & turnover to the City targeted for March

BUILDING 2

  • Building 2 – 705K SF spec cross-dock facility
  • Underground utilities substantially complete
  • Final grading & paving begin this month
  • Roll-up doors & glass framework are being installed
  • Landscaping starts in January
  • Delivery scheduled on track for March 2023