Check out the latest progress at Lakeland Central Park! We’re on track to deliver 705K SF of spec industrial space and three additional pad-ready sites representing 2.9M SF by Q1 2023
PHASE I INFRASTRUCTURE
- 3 pad-ready sites to accommodate 2.9M SF of industrial space
- Construction of Winston Park Boulevard, the spine road that will eventually run through the Park to connect Old Tampa Highway with Airport Boulevard will be complete by January 1
- Domestic Water, Storm System & Sanitary Sewer infrastructure on track to be complete by January 1
BUILDING 2
- Building 2 – 705K SF spec cross-dock facility
- Roof Structural Decking 100% Complete
- Rooftop Insulation/Exterior Membrane System 60% Complete
- Underground Utilities Underway